Civil Engineering Projects

Land Reclamation – Prima facility Trincomalee

Neat Solutions (PVT) ltd has taken over land reclamation work at Prima facility In Trincomalee and currently handling maintenance work until the handover after completion.

  • Total area cleared after excavation – 7.5 acre
  • Total area filled – 8.5 acre
  • Total area cleared and filled – 20 acre

Additional road construction work in project 3- Land Reclamation at Trincomalee was commenced on 17.02.2016 to 17.03.2016. The cost of this project was 3 million. It consisted of site mobilization, demolition of existing parts of the road, constructing new part of the road and demobilization.

Container unloading bay for rail freight – Prima (Seeduwa)

Design and Built project of a container unloading bay including the railway extension at Prima Ceylon (PVT) ltd factory in Seeduwa is commenced while further strengthening rail freight industry in Sri Lanka.

Harbour Dredging project – Delft Harbour, Jaffna

Neat Solutions (PVT) ltd successfully completed Delft harbour dredging and construction of pier projects in year 2012 for RDA, Sri Lanka. Further dredging of Delft harbour to increase maximum depth up to 2.5m was successfully completed.

Log Gates at CDL, Colombo port

The Design and Construction of Intermediate Gate at Dock NO 1 at Colombo Dockyard began on the 03/09/2011 and continued for a period of 72 days till 28/12/2011. The project was amounted to 62 million.

250 ton Bollard Testing Facility for CDL at Trincomalee

Commenced on the 16/03/2011, the 250 ton Bollard at Trincomalee Harbour was completed by the 20.04.2011. The project proposed by the client, Colombo Dockyard Limited, was estimated at the value of 11.2 million.

Slipways - SLNS

Navy- Renovation of Number 3 Slipway Underwater Railway Path at Sri Lanka Navy Dockyard, Trincomalee commenced during the month of January 2004. This project amounted to 11.2Million.

Colombo Dockyard Limited- Design of 1200TONS Slipways at Colombo Dockyard which amounted to 4Million. This project commenced on March 2005

K Port (PVT) ltd

Design and Consultancy for construction of inland container handling terminal facility for K Port (PVT) ltd at Orugodawatta.

Management consultancy in section 03 of A9 road construction, Jaffna.

The ADB Funded Road Network Improvement Project- Rehabilitation in Jaffna-Kandy (A9) Road in Northern Area was conducted under Access Engineering and performed a work up value up to 174Million from 199KM to 202KM, 275KM to 282KM and bypass road to Murugandy

Design and Consultancy of Mini Hydro Power Plant at Nayagan Ga, Deraniyagala.

Neat Solutions (Pvt) Ltd was the consult for the civil structures of Atabage Mini Hydro Power Plant of 2.3 MW capacity at Atabage, Gampola in Kandy district. The total cost of this project amounted to 6.5Million

Marine Projects

Marine construction – Club Bentota

Reconstruction of River Restaurant at Club Bentota Hotel, Bentota

Work was completed as per stated in the contract with Club Bentota which met its date of completion on February 2007. The amount was taken as 14Million.

  • Construction of a Boat Pier for Club Bentota Hotel, Bentota

The project was successfully completed and met its criteria and requirements by the completion date of May 2006. The total amount used for this project was 3Million.

Implementation and maintenance of silt curtain – Prima

For the first time in Sri Lanka, our diving team implemented and maintained a silt curtain (800m x 20m) that avoids sea water contamination and pollution while land reclamation operated at Prima Facility, China bay.

Randenigala bottom outlet

Equipped with umbilical codes and high tech underwater cameras, Neat Solutions (PVT) ltd diving team has repaired 60m deep mud gates at Randenigala bottom outlet.